第 73 题
章/节 专业英语  
 
 
(73) is pre-authorized by Change Management that has an accepted and established procedure to provide a specific charge requirement.
 
  A.  Emergency Change
 
  B.  Significant Change
 
  C.  Standard Change
 
  D.  Regular Change
 
 




 
 