全部科目 > 信息系统项目管理师 >
2012年下半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. (73) is false.
 
  A.  The communication management plan is contained in or is a subsidiary plan of, the project management plan.
 
  B.  The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
 
  C.  The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
 
  D.  The communication management plan can include guidelines project status meetings,project team
meetings,e-meetines,and e-mail
 
 




 
 
相关试题     专业英语 

  第73题    2012年上半年  
An example of scope verification is (73).

  第74题    2019年下半年  
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

  第75题    2009年下半年  
The creation of a work breakdown structure(WBS)is the process of(75)the major project deliverables.