Setting redundant componernts in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?(75)
 
  A.  risk avoidance
 
  B.  risk acceptance
 
  C.  risk mitigation
 
  D.  contingency plan
 
 




 
 
相关试题     专业英语 

  第73题    2020年下半年  
()is preservation of confidentiality, integrity and availability of information,in addition, other properties such as authenticity, accountability, non-repudiation and reliabilit..

  第73题    2014年上半年  
Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholder..

  第71题    2011年下半年  
Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools,which involves company actual or planned project practices to t..