In the (74)phase team members begin to work together and adjust their work habits and behaviors to support the team. The team learns to trust each other.
 
  A.  storming
 
  B.  performing
 
  C.  norming
 
  D.  adjourning
 
 




 
 
相关试题     专业英语 

  第73题    2018年下半年  
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctne..

  第71题    2012年上半年  
The connection between two networks to from an Internet is handled by a machine known as a(71).

  第73题    2014年上半年  
Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholder..