The following diagram denotes dependency between two activities A and B,It says()
.
 
  A.  B can’t start before A is finished
 
  B.  B can’t finish before A is finished
 
  C.  B can’t start before A starts
 
  D.  B can’t finish before A starts
 
 




 
 
相关试题     专业英语 

  第74题    2016年下半年  
Quality management ensures that an organization,product or service is (73)。It has four main components:quality planning,quality assurance,quality control and quality (74)。

  第72题    2013年上半年  
(72)is a collection of data sets,which is so large and complet that is because difficult to process using on hand database management tools or traditional data peocessing applica..

  第75题    2017年上半年  
()seeks to build confidence that a future output or an unfinished output, will be completed in a manner that meets the specified requirements and expectations.