2008年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
 
  A.  milestone
 
  B.  baseline
 
  C.  quality
 
  D.  work
 
 




 
 
相关试题     专业英语 

  第74题    2018年下半年  
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctne..

  第74题    2019年上半年  
Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management ..

  第75题    2010年下半年  
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.