2008年下半年 上午试卷 综合知识
第 75 题
知识点 ping  
章/节 专业英语  
 
 
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
 
  A.  analyze
 
  B.   track
 
  C.  level
 
  D.  extend
 
 




 
 
相关试题     专业英语 

  第71题    2017年下半年  
( ):a cloud service,allied to the set of business terms under which the cloud service is offered.

  第72题    2017年下半年  
( )is a computer technology that headsets ,sometimes in combination with physical spaces or multi-projected environments,to generate realisitic images ,sounds and other sensat..

  第75题    2013年上半年  
(75)is responsible for the attraction,selection,training,assessment,and rewarding of comployers,while also overseeing organizational leadership and cuiture and ensuring complianc..

 
知识点讲解
· ping
 
        ping
        ping通过发送"Internet控制报文协议(ICMP)"回送请求/应答报文来验证与另一台TCP/IP计算机的IP级连接。回送请求/应答报文的接收情况将和往返过程的次数一起显示出来。ping是用于检测网络连接性、可到达性和名称解析的疑难问题的主要TCP/IP命令。如果不带参数,ping将显示帮助。
        1)语法格式
        
        2)参数说明
        参数如下表所示。
        
        ping的选项
        



更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有