2016年上半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
The schedule management plan is a component of the project management plan. The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the (75) of the project, and includes appropriate control thresholds.
 
  A.  goals
 
  B.  values
 
  C.  needs
 
  D.  level
 
 




 
 