第 75 题
章/节 专业英语  
 
 
():The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies into the project.
 
  A.  Manage quality
 
  B.  Quality audit
 
  C.  Quality metrics
 
  D.  Quality improvement
 
 




 
 