第 73 题
章/节 专业英语  
 
 
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctness of the deliverables.
 
  A.  Perform Quality Assurance
 
  B.  Validate Scope
 
  C.  Control Quality
 
  D.  Define Scope
 
 




 
 