第 75 题
章/节 专业英语  
 
 
( ) is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
 
  A.  Analogous estimating
 
  B.  Parametric estimating
 
  C.  Three-point estimating
 
  D.  Bottom-up estimating
 
 




 
 
相关试题     专业英语 

  第74题    2013年上半年  
Software configuration management(SCM),is the task of tracking and controiling changes in the software,configuration management practices configuration identirication change contro..

  第74题    2009年下半年  
The Unified Modeling Language is a standard graphical language for modeling object-oriented software.(74)can show the behavior of systems in terms of how objects interact with e..

  第72题    2012年下半年  
A data warehouse is a subject-oriented data set used for reporting and analusis. Data warehouses can be subdivided into( 72). Which store subsets of data from a warehouse.




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有