Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management team assess and measure project performance and progress.
 
  A.  qulity
 
  B.  risk
 
  C.  change
 
  D.  cost
 
 




 
 