2019年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.
 
  A.  project scope statement
 
  B.  work package
 
  C.  WBS
 
  D.  project scope plan
 
 




 
 
相关试题     专业英语 

  第73题    2019年下半年  
( )is the process of managing procurement relationships , monitoring contract performance, and making changes and corrections as appropriate, and closing out contracts.

  第75题    2014年下半年  
The (75) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requir..

  第71题    2022年上半年  
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasi..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有