()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。
 
  A.  Validate scope
 
  B.  Define scope
 
  C.  Control scope
 
  D.  Collect requirement
 
 




 
 
相关试题     专业英语 

  第71题    2011年下半年  
Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools,which involves company actual or planned project practices to t..

  第73题    2022年下半年  
Project () includes making choices about: resource allocation,balancing competing demands, examining any alternative approaches, tailoring the processes to meet the project objec..

  第75题    2018年上半年  
():The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies into the project.




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有