(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
 
  A.  Quantitative Risk Analysis
 
  B.  Qualitative Risk Analysis
 
  C.  Enterprise Environmental Factors
 
  D.  Risk Management Plan
 
 




 
 
相关试题     专业英语 

  第73题    2011年下半年  
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity ..

  第75题    2020年下半年  
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and incr..

  第75题    2012年下半年  
The most crucial time for project risk assessment is (75).




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有