第 72 题
章/节 专业英语  
 
 
()is a grid that shows the project resources assigned to each work package.
 
  A.  Stakeholder engagement assessment matrix
 
  B.  Requirements traceability matrix
 
  C.  Probability and impact matrix
 
  D.  Responsibility assignment matrix
 
 




 
 