第 73 题
章/节 专业英语  
 
 
Project () includes making choices about: resource allocation,balancing competing demands, examining any alternative approaches, tailoring the processes to meet the project objectives and managing the interdependencies among the Project Management Knowledge Areas.?
 
  A.  schedule management
 
  B.  scope management
 
  C.  integration management
 
  D.  resource management
 
 




 
 
相关试题     专业英语 

  第75题    2008年下半年  
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can requ..

  第75题    2019年下半年  
Risk( )acknowledge the existence of a threat,but no proactive action is taken 。

  第73题    2011年上半年  
Documentation of a software package is normally produced for two purposes.One is to explain the(71)of thesoftware and describe how to use them.This is known as(72)because it is des..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2023 All Rights Reserved
软考在线版权所有