2022年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
Project()management includes the processes required to identify the people, groups or organizations that could impact or be impacted by the project,to analyze their expectations and impact on the project,and to develop the appropriate management strategies for effectively engaging them in project decisions and execution.?
 
  A.  supplier
 
  B.  customer
 
  C.  resource
 
  D.  stakeholder
 
 




 
 
相关试题     专业英语 

  第71题    2008年下半年  
Define Activities is the process of identifying the specific actions to be performed to produce the (71).

  第75题    2009年下半年  
The creation of a work breakdown structure(WBS)is the process of(75)the major project deliverables.

  第75题    2022年上半年  
Advancements in ()have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.