2017年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
( )is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk ,and evaluating risk process effectiveness throughout the project。
 
  A.  Identify risks
 
  B.  Control risks
 
  C.  Plan risk responses
 
  D.  Plan risk management
 
 




 
 