Schedule development can require the review and revision of duration estimates and resource estimates to create an approved (74) that can serve as a baseline to track progress.
 
  A.  scope statement
 
  B.  Activity list
 
  C.  project charter
 
  D.  Project schedule
 
 




 
 
相关试题     专业英语 

  第73题    2014年上半年  
In project management , a (73 ) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often esti..

  第72题    2012年下半年  
The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and methodologies that people use to develop these systems. Seque..

  第72题    2019年下半年  
( )seeks to perform root cause investigation as to what is Ieading identified trends.