全部科目 > 系统集成项目管理工程师 >
2009年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
The Development of Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
 
  A.  Project Scope Statement
 
  B.  Project Management Plan Project
 
  C.  Forecasts
 
  D.  Charte
 
 




 
 
相关试题     专业英语 

  第73题    2021年下半年  
The highest level of quality management is ().

  第74题    2019年下半年  
( )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.

  第73题    2013年下半年  
(73) is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation and review techniques).




更多复习资料