Configuration management is focused on the specification of both the deliverables and the processes;While ( ) is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.
 
  A.  cost management
 
  B.  change management
 
  C.  configuration management
 
  D.  capacity management
 
 




 
 
相关试题     专业英语 

  第74题    2019年下半年  
( )is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics.

  第75题    2009年下半年  
The Development of Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

  第72题    2012年下半年  
The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and methodologies that people use to develop these systems. Seque..