全部科目 > 系统集成项目管理工程师 >
2013年下半年 上午试卷 综合知识
第 73 题
关键词 PERT  
章/节 专业英语  
 
 
(73) is not the advantage of GERT(graphical evaluation and review techniques) as compared with PERT(project evaluation and review techniques).
 
  A.  Allowing looping
 
  B.  Allowing for dummy tasks
 
  C.  Allowing branching
 
  D.  Allowing multiple project end results
 
 




 
 
相关试题     专业英语 

  第72题    2010年下半年  
Most of the host operating system provides a way for a system administrator tomanually configure the IP information needed by a host.Automated configuration methods,such as (72),..

  第71题    2018年上半年  
( ) is a programming model and an associated implementation for processing and generating big data sets with a parallel, distributed algorithm on a cluster. The model is a specia..

  第75题    2011年下半年  
The work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the(75).