Many of the activities performed during the preliminary investigation are still being conducted in (71).but in much greater depth than before. During this phase, the analyst must become fully aware of the(72)and must develop enough knowledge about the(73)and the existing systems to. enable an effective solution to be proposed and implemented. Besides the(74)for process and data of current system,the deliverable from this phase also includes the(75)for the proposed system.
 
  A.  analysis phase
 
  B.  design phase
 
  C.  implementation phase
 
  D.  maintenance phase
 
 




 
 
相关试题     专业英语 

  第75题    2011年上半年  
The analysis phase answers the questions of who will use the system, what the system will do, and where and when it will be used. During this phase, the project team investigates a..

  第73题    2016年上半年  
A variety of tools is available to help the analyst to discover the users' true needs. These tools are grouped into three broad techniques that are based on the degree of change an..

  第75题    2022年上半年  
Requirements validation is the process of checking that requirements actually define the system that the customer really wants. It overlaps with analysis as it is concerned with fi..