A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for (72).
 
  A.  identifying individual tasks for a project
 
  B.  scheduling the start of tasks
 
  C.  scheduling the end of tasks
 
  D.  determining potential delays
 
 




 
 
相关试题     专业英语 

  第73题    2015年上半年  
(73)is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。

  第71题    2021年上半年  
()describes how the information about the items of the project will be recorced and updated so that the product,service,or result ofthe proiect remains consistent and operative.

  第74题    2012年下半年  
Quality management (74).