第 74 题
章/节 专业英语  
 
 
Performing (74) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
 
  A.  quality planning
 
  B.  quality assurance
 
  C.  quality performance
 
  D.  quality control
 
 




 
 