2014年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
 (75) is one of the quality planning outputs.
 
  A.  Scope base line
 
  B.  Cost of quality
 
  C.  Product specification
 
  D.  Quality checklist
 
 




 
 
相关试题     专业英语 

  第73题    2016年上半年  
The cost performance index(CPI)is the ratio of earned value to(73)and can be used to estimate the projected cost of completing the project.

  第71题    2011年下半年  
The prototyping method is a dynamic design processes,which requires people who use prototyping method to have the following capability of (71) .

  第71题    2013年下半年  
Since risk is associated with most projects, the best course of action is to (71)