2015年上半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
(75)is the application of planned, systematic quality activities to ensure that the project will employ all processes to meet requirements.
 
  A.  Quality assurance
 
  B.  Quality planning
 
  C.  Quality control
 
  D.  Quality cost
 
 




 
 