关键词 CPI  
章/节 专业英语  
 
 
The cost performance index(CPI)is the ratio of earned value to(73)and can be used to estimate the projected cost of completing the project.
 
  A.  cost variance
 
  B.  planned cost
 
  C.  Schedule Variance
 
  D.  actual cost
 
 




 
 