  第73题      
  章/节:   专业英语       

 
The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. (73) is false.
 
 
  A.  The communication management plan is contained in or is a subsidiary plan of, the project management plan.
 
  B.  The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.
 
  C.  The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
 
  D.  The communication management plan can include guidelines project status meetings,project team
meetings,e-meetines,and e-mail
 
 
 

 
  第72题    2010年下半年  
   81%
Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that mo..
  第71题    2019年下半年  
   74%
( )seeks to perform root cause investigation as to what is leading identified trends.
  第73题    2021年下半年  
   59%
()the process of determing documenting and managing stakeholder needs and requirements to meet project objectives.
   题号导航      2012年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第73题    在手机中做本题