第75题      2018年上半年 信息系统项目管理师 上午试卷 综合知识
所属知识点   专业英语             

 
():The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies into the project.
 
 
  A.  Manage quality
 
  B.  Quality audit
 
  C.  Quality metrics
 
  D.  Quality improvement
 
 
 



↓第75题
  专业英语 知识点 更多相关真题:    更多>>  
 
  第72题    2016年上半年  
(72):a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it.
  第73题    2018年上半年  
( )includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . managing the pro..
  第74题    2015年上半年  
74、Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an el..
 
题号导航      2018年上半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况
第1题 /
第2题 /
第3题 /
第4题 /
第5题 /
第6题 /
第7题 /
第8题 /
第9题 /
第10题 /
第11题 /
第12题 /
第13题 /
第14题 /
第15题 /
 
第16题 /
第17题 /
第18题 /
第19题 /
第20题 /
第21题 /
第22题 /
第23题 /
第24题 /
第25题 /
第26题 /
第27题 /
第28题 /
第29题 /
第30题 /
 
第31题 /
第32题 /
第33题 /
第34题 /
第35题 /
第36题 /
第37题 /
第38题 /
第39题 /
第40题 /
第41题 /
第42题 /
第43题 /
第44题 /
第45题 /
 
第46题 /
第47题 /
第48题 /
第49题 /
第50题 /
第51题 /
第52题 /
第53题 /
第54题 /
第55题 /
第56题 /
第57题 /
第58题 /
第59题 /
第60题 /
 
第61题 /
第62题 /
第63题 /
第64题 /
第65题 /
第66题 /
第67题 /
第68题 /
第69题 /
第70题 /
第71题 /
第72题 /
第73题 /
第74题 /
第75题 /