免费智能真题库 > 历年试卷 > 信息系统项目管理师 > 2010年下半年 信息系统项目管理师 上午试卷 综合知识
  第71题      
  章/节:   专业英语       

 
Project schedule management is made up of six management processes including:activity definition, activity sequencing, (71) , and schedule control by order.
 
 
  A.  activity duration estimating, schedule developing, activity resource estimating
 
  B.  activity resource estimating, activity duration estimating, schedule development
 
  C.  schedule developing, activity resource estimating, activity duration estimating
 
  D.  activity resource estimating, schedule developing, activity duration estimating
 
 
 

 
  第74题    2019年下半年  
   47%
The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish t..
  第71题    2020年下半年  
   57%
The patterns of()show the next probable behavior of a person or market without a logical explanation as to why.
  第72题    2019年上半年  
   45%
( ) is an open, distributed ledger that can record transations between two parties efficiently and in a verifiable and p..
   题号导航      2010年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第71题    在手机中做本题