  第73题      
  章/节:   专业英语       

 
The project management plan defines how the project is executed,monitored and controlled , and closed . it is progressively elaborated by updates , and controlled and approved through the Perform Integrated( )process.
 
 
  A.  Cost control
 
  B.  Schedule Control
 
  C.  Change Control
 
  D.  Risk Control
 
 
 

 
  第73题    2014年上半年  
   63%
”Cost of quality ”is a project management concept that includes cost of ( ).
  第71题    2014年下半年  
   43%
Most of the host operating system provides a way to automated configure the IP information needed by a host Automated co..
  第74题    2019年下半年  
   62%
When required,the Perform Integrated Change Control process includes a ( ),Which is a formally chartered group respons..
   题号导航      2017年下半年 信息系统监理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第73题    在手机中做本题