第74题      2019年下半年 信息系统监理师 上午试卷 综合知识
所属知识点   专业英语       

 
When required,the Perform Integrated Change Control process includes a ( ),Which is a formally chartered group responsible for reviewing,evaluating,approving, deferring, or rejecting changes to the project and for recording and communicating such decisions.
 
 
  A.  BBC
 
  B.  CCB
 
  C.  BCB
 
  D.  CBC
 
 
 

  专业英语 知识点 更多相关真题:    更多>  
 
  第73题    2014年上半年  
   66%
”Cost of quality ”is a project management concept that includes cost of ( ).
  第75题    2019年下半年  
   61%
( )are also known as tally sheets are used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem. They are ..
  第72题    2012年下半年  
   66%
Supervision will manage the implementation and the configuration of the different types of project documents, not including (72).
 


 题号导航      2019年下半年 信息系统监理师 上午试卷 综合知识   本试卷我的完整做题情况 
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
↓第74题